Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of September 25, 2007
Description:
Testimony issued by the Government Accountability Office with an abstract that begins "Since the July 31, 2007, Capitol Visitor Center (CVC) hearing, the project's construction has progressed, and Architect of the Capitol (AOC) is now anticipating a November 2008, opening date. In addition, AOC and the sequence 2 contractor have signed a contract modification that extends the date for completing the majority of the sequence 2 work from September 15, 2006 to November 15, 2007. However, because d…
more
Date:
September 25, 2007
Creator:
United States. Government Accountability Office.
Item Type: