Geothermal commercial power plant study. Monthly progress report, September 25-October 22, 1976
Description:
Efforts were concentrated on plant operating modes. The Heber plant, which was previously designed for consistant brine temperature, was reviewed and changes necessary to accomodate declining brine temperature were determined. Resultant required modifications to the computer code GEOTHM were made. The engineering, in terms of sketches and equipment lists, needed to support the capital cost estimate was determined. Attempts to use the computer program GEOTHM to develop the heat and mass balances…