Development and testing of industrial scale, coal fired combustion system, Phase 3
Description:
A major part of the work in this quarter was on the combustor tests in task 2. Three of the six planned tests in this task were completed. The first two were parametric tests of nominal one shift, (8 hour) duration on coal. Due to failure of the UV detector in the first test only several hours of coal fired operation were completed. In the second test, coal fired operation continued for the planned one shift until the 4 ton coal bin was empty. After reviewing this work with DOE, it was decided …