Hanford Atomic Products Department. Monthly report, June 1966
Description:
The programmed long outage which started May 1 was concluded on June 6. During this outage, the sixth heat exchanger cell was tied in, the auxiliary steam boiler was completely overhauled, four steam generators were equipped with isolation valves, extensive replacements of the process tube resistance temperature detectors were made, the reactor was re-orificed, a leaking reactor gas seal was repaired, extensive preventive maintenance was done, and numerous smaller pieces of work were accomplish…