Search Results

open access

X/Qs and unit dose calculations for Central Waste Complex interim safety basis effort

Description: The objective for this problem is to calculate the ground-level release dispersion factors (X/Q) and unit doses for onsite facility and offsite receptors at the site boundary and at Highway 240 for plume meander, building wake effect, plume rise, and the combined effect. The release location is at Central Waste Complex Building P4 in the 200 West Area. The onsite facility is located at Building P7. Acute ground level release 99.5 percentile dispersion factors (X/Q) were generated using the GXQ.… more
Date: April 3, 1996
Creator: Huang, C. H.
Partner: UNT Libraries Government Documents Department
Back to Top of Screen