100-N temporary construction line considerations
Description:
Present thinking and planning appears to be developing from the following factors as concern the 13.8 KV temporary construction power limit. 1. It is understood that the present intent is to supply 100-N operating requirements from a single stub source in the 230 KV loop. 2. The original thoughts were to obtain construction power over a 13.8 KV line from 151-D substation. 3. Construction load requirements are now less than originally planned since steam has been substituted for electrical drive…
more
Date:
December 30, 1958
Creator:
Mollerus, F. J.
Partner: