D0 Silicon Upgrade: Upgrade Piping Loads on Cleanroom Roof
Description:
The proposed piping layout for the DO upgrade will run along the south wall of DAB. The cryogenic service pipe runs above the upper and lower cleanroom roofs and will need to be supported by the roofs beams. Calculations were done to determine the stresses in the I-beams created by the existing and additional loads due to the upgrade. Refer to drawing no. 3823.115-ME-317283 for drawings of the piping layout. Figure 1 shows the 'plan view' portion of this drawing. The weight of the individual li…
more
Date:
August 28, 1995
Creator:
Sakla, Steve
Partner: