Determination of reactivity coefficients and rod calibration of D Pile. Interim report on Production Test No. 105-97-P
Description:
The test of March 7, 1947 was planned as a check on power coefficient values; however, an analysis of reactivity data gave evidence of a considerable flattening of ``A`` rod in the region between 0--75 inches out. A second test of longer duration was therefore made on April 1, 1947 in order to obtain a check calibration of this portion of the control rod. The results of this test verified the flattening of this portion of ``A`` rod. The redetermined power coefficients based on new rod calibrati…
more
Date:
April 25, 1947
Creator:
Kruesi, F. E.
Partner:
UNT Libraries Government Documents Department