Douglas United Nuclear, Inc. and the National Defense Program
Description:
This report presents the results of an updated study to determine the preparation, schedules and cost for restart of KE Reactor and the subsequent plutonium production and incremental conversion cost of sustained plant operation. The restart of Hanford`s KE Reactor features short startup time, large capacity, low cost, and high purity product. The study shows that KE Reactor can be restarted and achieve full power 7 months after authorization. Prestartup costs are $4,416,000 for labor and mater…
more
Date:
April 21, 1972