Search Results

open access

Gas/Liquid Membranes for Natural Gas Upgrading Quarterly Report: Number 9

Description: Efforts this quarter have concentrated on field site selection. ChevronTexaco has signed a contract with Kvaerner process Systems for the 50 MM scf/d dehydration skid at their Headlee Gas Plant in Odessa, TX for a commercial-scale test. This will allow the test to go forth. A new test schedule was established with testing beyond the existing contract completion date. Potting and module materials testing continued. Construction of the bench-scale equipment was started. Additional funding to supp… more
Date: January 1, 2004
Creator: Meyer, Howard S.
open access

Gas/Liquid Membranes for Natural Gas Upgrading Quarterly Report: Number 10

Description: Efforts this quarter have concentrated on field site selection. ChevronTexaco has signed a contract with Kvaerner process Systems for the 50 MM scf/d dehydration skid at their Headlee Gas Plant in Odessa, TX for a commercial-scale test. This will allow the test to go forth. A new test schedule was established with testing beyond the existing contract completion date. Potting and module materials testing continued. Construction of the bench-scale equipment was started. Additional funding to supp… more
Date: April 1, 2004
Creator: Meyer, Howard S.
open access

Gas/Liquid Membranes for Natural Gas Upgrading Quarterly Report: Number 11

Description: Efforts this quarter have concentrated on design and planning for of a 50 MM scf/d dehydration skid testing at ChevronTexaco's Headlee Gas Plant in Odessa, TX. Potting and module materials testing continued. Construction of the bench-scale equipment continued. Additional funding to support the test was obtained through a contract with Research Partnership for Secure Energy for America. GTI has decreased the effort under this contract pending DOE's obligation of the total contract funding.
Date: July 1, 2004
Creator: Meyer, Howard S.
open access

Gas/Liquid Membranes for Natural Gas Upgrading Quarterly Report: Number 12

Description: Efforts this quarter have concentrated on design and planning for of a 50 MM scf/d dehydration skid testing at ChevronTexaco's Headlee Gas Plant in Odessa, TX. Potting and module materials testing concluded. Construction of the bench-scale equipment continued and a pre-engineering study on a subsea application of the technology was performed cofunded contracts with Research Partnership for Secure Energy for America and Gas Research Institute. GTI has decreased the effort under this contract pen… more
Date: October 1, 2004
Creator: Meyer, Howard S.
Back to Top of Screen