Acceptance test report 2721-Z upgrades
Description:
This test procedure provides instructions for acceptance testing of modifications to the 2721-Z diesel-generator system made by Project C-189. The modifications include (1) replacing the generator NUMA-LOGIC controller with connection to the PFP distributed control system (DCS), (2) replacing ATSI with a breaker switching scheme for 2736-ZB backup power and (3) providing a method for generator load and system testing.
Date:
February 3, 1998
Creator:
Keck, R. D.
Item Type:
Refine your search to only
Report